Pictures

Tentative work schedule:

June 28th week:
Dish room hood installation.
Convection oven venting.
Finish Electrical & Plumbing.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

Work Completed.

June 25th

Kitchen hood finished and tested.
Fire Marshall approved.
Building Inspector gave occupancy.
Sam's Siren installed and tested.

June 7-12

More hood work.
More kitchen equipment delivered.
Walk-in cooler/freezer installed.
More plumbing & electrical.

June 1-5

Deck completed and passed inspection.
Kitchen hood installation started.
Some sinks & counters installed.
More electrical & plumbing.
More painting & cleaning.
Front posts & downspouts installed.

May 24-31, 2010

More kitchen equipment delivered.
More electrical & plumbing.
Deck almost completed.
All drywall finished & painted.
Kitchen suspended ceiling started.
FRP installed in dish room.
Vinyl baseboard installed.
Some doors & trim installed.

May 16-20, 2010

Last drywall installed.
Drywall finishing & sanding.
More painting.
More deck construction.
Propane tank & line installed.
Work in old messhall.

May 10-15, 2010

Drywall installed in kitchen & dishroom.
More painting done.
Floors painted in office and canteen.
Deck Construction continued.
Concrete pad poured for deck stairs.
Nurse uppper cabinets installed.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

May 3-8, 2010

Drywall finish & painting in office and canteen.
Concrete sidewalks and cooler pad finished.
Doors and trim in office and canteen.
Deck Footings in.
Nurse cabinets, counter & sink installed.
More painting done.
Lots of mowing.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

May 1, 2010

Grand Opening!

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

April 25-30, 2010

Front & Back sidewalks poured.
AC Units installed.
New siding on Apache, Nunami and Blackfoot cabins.
Apache, Nunami and Blackfoot cabins painted.
Dining Hall Plumbing and Electrical rough-in completed.
Electricity connected to boys cabins.
More remodeling of old mess hall.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

April 23-24, 2010

150 NRD trees planted.
Trees and shrubs transplanted from tree nursery.
Drywall finishing, sanding, priming and painting.
More remodeling in old messhall.
More kitchen equipment delivered.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

April 16-18, 2010

Power Poles installed.
Painting in new Craft room.
Sheetrock installed in new Dining Hall.
Sam's Siren delivered.
Four new picnic tables delivered.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

April 9-10, 2010

Some kitchen equipment delivered.
Septic system installed.
Incinerator moved.
Old mess hall remodeling.
Replaced bottom wall boards with treated lumber.
Dead trees removed for power lines.
Dirt work around girls cabins and new Dining Hall.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

April 1-3, 2010

Subcontractor sealed Dining Hall floor.
Remodeling of old mess hall.
cleared brush for dirt work.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

March 27, 2010

Built walls for office and canteen.
Built walls for classroom.
Built walls in craft room.
Installed, cleaned and painted cupboards in Craft room.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

March 20, 2010

Taped & first coated sheetrock.
Removed old siding from 2 cabins.
Hauled trash to dump.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

March 13, 2010

Cleaned out old kitchen.
Cleaned out office and canteen.
Began installing sheetrock.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

March 6, 2010

Installed insulation.
Installed window in nurse's room.
Cleaned out everything for floor finishing.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

February 27, 2010

Sheeted floor above dish room, janitor closet and nurse's room for storage.
Framed walls above rooms.
Installed fold-down ladder.
Cleaned out everything for floor finishing.

Electrical rough-in for exterior walls is done.
Electrical inspection has been completed.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

February 23, 2010

To all Nebraska Youth Camp volunteer laborers:

(Ephesians 3:20) Praise God for blessing His Nebraska Youth Camp Ministry beyond our imagination!

The new Camp Dining Hall is finally becoming a reality. Our goal is to have it fully operational before camp starts!

BD Construction and their subcontractors are still working on their part of the project.
The steel frame is complete. The bathrooms and utility room are completed. The list of what they have left to do:
Interior:
Re-do Seal of colored concrete floor.
Caulk concrete around beam supports.
Seal floor in furnace room.
Exterior:
Install downspouts

Thank you,
Nebraska Youth Camp
Facilities Committee


This page © Copyright 2005, Jake Munsell